Select Page

Asapokhai
Question 1 What are key attributes of a project?   Be permanent;…

Question 1

What are key attributes of a project?

 

Be permanent; without an end date and deliverables

 

Specific time frame, clear objective, unique

 

Reoccurring, routine part of an operation

 

Unlimited time and resources

 

Unrelated to client needs

Question 2

 

“Each project has many interested internal and external parties or “customers.” Often these individuals change or their interests in the project change during the different phases of the project. This may cause the other “technical” requirements—which we may have assumed to be stable—to likewise change. Interestingly, there are a number of nontechnical requirements that usually never change but are forgotten.” (PMI,2023)

 

What group of people best identity the statement above?

 

Resources

 

Government

 

Project stakeholders

 

PMI

 

Legislators

Question 3

 

What are the most relevant organization and knowledge resource for the Project Management profession in North America?

 

United Nations (UN) and its UN Chart from 1945

 

Project Management Institute(PMI), Guide to the Project Management Body of Knowledge (PMBOK® Guide)

 

European Projects Association(EPA), My Europe Platform

 

Project Management Office (PMO), Project Management Book

Question 4

 

The Project Charter is a document that:
 

Assigns resources for specificdaily tasks

 

Defines all the details of a project plan

 

Closes a project

 

Schedules project activities

 

Authorizes initiating a project

Which project document should first define its purpose?

 

Project budget

 

Project Charter

 

Work Breakdown Structure

 

Project Schedule

 

Scope change control

Question 9

0.75 Points

Who gives formal authorization for a project to start?

 

Project Manager

 

Project Coordinator

 

Project Sponsor

 

Project Consultant

 

Finance Manager

Question 10

0.75 Points

Organizations directly manage and implement their projects “in house” when:

 

they do not have the resources for the project

 

do not have the required expertise for the project

 

they have internally the required resources and expertise

 

they outsource project related work to contractors

 

they do not want to start a project

Question 11

0.75 Points

What is the main purpose of a Request for Proposal (RFP)?

 

To outline the requirements for a specific project to solicit bids from vendors and identify which one is best qualified to complete the project.

 

To document when an organization is directly managing and implementing their projects “in house”.

 

To be the main legal agreement, contract between the organization and contractor.

 

To be the main document to track all scope changes.

 

To define the project plan and schedule in details.

Question 12

0.75 Points

When an organization aims to start a project, but wants to contract external services to carry out the project, it may launch a:

 

Project agreement

 

Request for Proposal (RFP)

 

Project Charter

 

Project Schedule

 

Project Budget

Question 13

 

These are key RFP contents related to defining project objective and scope of work:

 

Evaluation criteria, due date, costs

 

Project objective, Statement of Work (SOW), customer requirements,

 

Due date, schedule

 

Budget, financial resources

 

Time, Gantt Chart

Question 14

 

These are key RFP contents related to project timing:

 

Evaluation criteria, costs

 

Project objective, Statement of Work (SOW), customer requirements,

 

Required schedule and due date

 

Budget, financial resources

 

Project deliverables

Question 15

 

Considering that customer organizations, as clients, prefer to work with people they know and trust, before submitting a proposal to a RFP, it is important for participating contractors/bidders to:

 

Start hiring resources as soon as possible

 

Develop project schedules well in advance

 

To ensure they always provide the lowest price

 

To ensure they always provide the best quality

 

Build relationships with customers, partners

Question 16

 

In order to be successful as a competitive business, project contracting requires anticipated:

 

Marketing

 

Municipal approval

 

Contingency reserves

 

Building Permit

 

Certificate of Insurance

Question 17

 

These are key items to consider before a contractor makes a decision to develop a proposal for a RFP:

 

Risks, proposal resources, project resources

 

Certificate of Insurance

 

Municipal approval

 

Contingency reserves

 

Building Permit

Question18

 

Considering the proposal process for a RFP is competitive, the customer will select that one that is expects will provide the best value. What are the most relevant technical contents of a competitive proposal?

 

Understanding the need, proposed approach/solution, benefits to the customer

 

The lowest price, the best cover page

 

The longest proposal, excellent formatting

 

The best visual presentation

 

The most qualified, educated resources

Question 19

 

Considering the management section of a proposal should be able to demonstrate the contractor can do the proposed work and achieve the intended results, it should contain:

 

Certificate of Insurance, the lowest price

 

Municipal approval, Building Permit

 

Reference letters, statement of previous clients

 

Contingency reserves, the best visual presentation

 

Deliverables, Project schedule, project organization, related experience

 

Question 5

 

The Project Charter is a document that:

Assigns resources for specificdaily tasks

 

Defines all the details of a project plan

 

Closes a project

 

Schedules project activities

 

Authorizes initiating a project

 

Question 6. Which project document should first define its purpose?

 

Project budget

 

Project Charter

 

Work Breakdown Structure

 

Project Schedule

 

Scope change control

Question 7

 

Who gives formal authorization for a project to start?

 

Project Manager

 

Project Coordinator

 

Project Sponsor

 

Project Consultant

 

Finance Manager

Question 8

 

Organizations directly manage and implement their projects “in house” when:

 

they do not have the resources for the project

 

do not have the required expertise for the project

 

they have internally the required resources and expertise

 

they outsource project related work to contractors

 

they do not want to start a project

 

Question 9. What is the main purpose of a Request for Proposal (RFP)?

 

To outline the requirements for a specific project to solicit bids from vendors and identify which one is best qualified to complete the project.

 

To document when an organization is directly managing and implementing their projects “in house”.

 

To be the main legal agreement, contract between the organization and contractor.

 

To be the main document to track all scope changes.

 

Question 10

When an organization aims to start a project, but wants to contract external services to carry out the project, it may launch a:

 

Project agreement

 

Request for Proposal (RFP)

 

Project Charter

 

Project Schedule

 

Project Budget

 

Question11.

These are key RFP contents related to defining project objective and scope of work:

 

Evaluation criteria, due date, costs

 

Project objective, Statement of Work (SOW), customer requirements,

 

Due date, schedule

 

Budget, financial resources

 

Time, Gantt Chart

Question 12

These are key RFP contents related to project timing:

 

Evaluation criteria, costs

 

Project objective, Statement of Work (SOW), customer requirements,

 

Required schedule and due date

 

Budget, financial resources

 

Project deliverables

Question 13

 

Considering that customer organizations, as clients, prefer to work with people they know and trust, before submitting a proposal to a RFP, it is important for participating contractors/bidders to:

 

Start hiring resources as soon as possible

 

Develop project schedules well in advance

 

To ensure they always provide the lowest price

 

To ensure they always provide the best quality

 

Build relationships with customers, partners

 

Question 14

 

These are key items to consider before a contractor makes a decision to develop a proposal for a RFP:

 

Risks, proposal resources, project resources

 

Certificate of Insurance

 

Municipal approval

 

Contingency reserves

 

Building Permit

Question 15

 

Considering the management section of a proposal should be able to demonstrate the contractor can do the proposed work and achieve the intended results, it should contain:

 

Certificate of Insurance, the lowest price

 

Municipal approval, Building Permit

 

Reference letters, statement of previous clients

 

Contingency reserves, the best visual presentation

 

Deliverables, Project schedule, project organization, related experience